The construction of the comfort-class residential complex “Svyatobor Park Resort” by City One Development continues to progress.
Meanwhile, buildings from phases 6 and 7 of the complex are steadily growing. Here’s a detailed report from the construction site:
Phase 6
- In Section 3, formwork installation for pouring columns and vertical elements of the 5th floor has been completed.
- In Section 4, reinforcement and formwork installation for pouring the ceiling slab of the 6th floor has been completed.
Phase 7
- In Section 1, internal and external walls up to the 5th floor have been fully laid with bricks.
- In Section 2, formwork has been installed and concrete pouring for the ceiling slab of the 12th floor is in progress.
- In Section 3, concrete columns and vertical elements of load-bearing walls for the 12th floor have been poured.
- Formwork has been installed and preparation for pouring concrete for the ceiling slab between the 12th and 13th floors is ongoing.
- External wall brickwork up to the 5th floor is nearing completion.
Investors and future apartment owners in the 7th phase of the Svyatobor residential complex can already visit, inspect, or choose the best option for their future homes.
We invite you for a professional consultation at our sales department:
📍 15-B Lvivska Street
📲 097 259 39 52
📲 067 583 30 40