The investment and development company City One Development sincerely thanks the investors for their trust. Thanks to timely payments in installments and the effective work of the company’s specialists, we maintain a high pace of construction.
Traditionally, at the end of the month, we share the achievements from the construction sites of phases 7 and 8 of the “Novopecherski Lypky” residential complex:
Phase 7 (building project numbers 1, 2, 3, 4)
Building No. 1
- Started installing entrance apartment doors.
- Installing engineering networks for water supply and drainage, as well as low-voltage alarm and automation systems.
- Completing insulation of the building with non-combustible mineral wool and installing profiles for ventilated facade.
- Ongoing work on the installation of aluminum window glazing and facade structure.
Building No. 2
- Completing installation of fire safety systems and heating, sewage, and water supply systems in the parking area between buildings 2 and 3.
- Installing engineering networks for water supply and drainage, low-voltage alarm and automation systems, and pumping systems for water supply.
- Ongoing insulation of the building with mineral wool, fastening of protective geomembrane, and installation of ventilated facade.
- Continuing installation of aluminum window glazing and facade structure.
Building No. 3
- Continuing installation of engineering networks for water supply and drainage, low-voltage alarm and automation systems, and inflow-exhaust ventilation.
- Completing insulation of the building with non-combustible mineral wool and installation of ventilated facade.
- Continuing installation of aluminum window glazing and facade structure.
Building No. 4
- Continuing installation of entrance apartment doors.
- Installing engineering networks for water supply and drainage, as well as low-voltage alarm and automation systems.
- Completing installation of aluminum window glazing and glazing of window elements.
Phase 8 (building project numbers 5, 6, 9)
Building No. 6
- The monolithic frame of the building has grown to the 11th floor. Construction of floors 12-13 is in progress.
- Continuing masonry of external and internal walls on floors 8-9.
- Continuing the arrangement of the underground parking under buildings 5-6.
Building No. 5
- Continuing installation of elevator and technological equipment.
- Arranging ventilation systems and installing water supply and drainage risers.
- Arranging systems: fire safety, alarm, dispatching, and automation.
Club-format Building No. 9
- Continuing installation of elevator equipment, elevator cabins, and technological equipment.
- Ongoing installation of water supply and drainage risers and ventilation systems on the floors and roof of the building.
- Continuing the arrangement of systems: fire safety, alarm, dispatching, and automation.
- Completing masonry of internal walls in the underground parking.