City One Development, the investment and development company, plans to complete the construction of the 7th phase and commence the 8th phase of the “Novopecherski Lipki” business-class quarter this year.

To expedite the handover of homes to investors, construction activities on the sites continue without interruption. Here are the detailed updates on the work and progress of construction for the current month:

Phase 7 (Building Project Numbers 1, 2, 3, 4)

Building 1

  • Completed installation of apartment doors.
  • Ongoing installation of floor electrical panels and cable products for apartments and common areas.
  • Radiator installation in apartments is in progress.
  • Commenced finishing works in the entrance groups.
  • Completion of installation of ventilated facade and insulation of the building with non-combustible mineral wool.
  • Installation of aluminum window glazing and facade structure glazing is in final stages.
  • Completed installation of ventilation and heating systems in the underground parking.
  • Installation of entrance gates in the parking area is completed.
  • Finalizing architectural lighting installation.
  • Landscaping of the surrounding territory is ongoing.

Building 2

  • Finished installation of doors in common areas.
  • Completed plastering works.
  • Glazing of the facade of the two-story commercial building connecting buildings 2 and 3 is fully completed.
  • Completion of interior elevator equipment installation.
  • Construction of transitions from buildings 2-3 to the central street of the quarter is ongoing.
  • Final stage installation of entrance gates in the parking area.
  • Completed glazing of above-ground railings of skylight windows in the stylobate part of the underground parking.
  • Continued insulation with mineral wool and installation of ventilated facade.
  • Ongoing installation of architectural lighting and glazing of windows and facade structures.
  • Landscaping works for the surrounding territory continue.

Building 3

  • Completed insulation with mineral wool and nearing completion of ventilated facade installation.
  • Finalizing installation of window elements on the parapet part of the building.
  • Finalizing plastering, cement-sand screeding, and installation of KAN water supply system piping in apartments.
  • Radiator installation in apartments is ongoing.
  • Continuing installation of facade lighting.
  • Landscaping of the surrounding territory is ongoing.

Building 4

  • Started finishing works in the entrance groups.
  • Completed installation of apartment doors.
  • Radiator installation in apartments is ongoing.
  • Completed installation of window elements on the parapet part of the building.
  • Ongoing installation of floor electrical panels and cable products for apartments and common areas.
  • Completed installation of entrance gates in the parking area.
  • Completion of architectural lighting installation.
  • Ongoing landscaping of the surrounding territory.

Continuing works on the installation of internal courtyard engineering networks (drainage systems, sewerage, water supply, etc.) for all buildings of Phase 7.

Phase 8 (Building Project Numbers 5, 6, 9)

Club-format Building 9

  • Installation of aluminum window glazing frames and installation of transparent facade structures from floors 1 to 16 are ongoing.
  • Continued installation of fire safety systems and signaling, dispatching, and automation systems.
  • Flooring installation in the underground parking is ongoing.

Building 5

  • Installation of aluminum window glazing frames and installation of transparent facade structures from floors 2 to 21 are ongoing.
  • Near completion of installation of fire safety systems and signaling, dispatching, and automation systems.
  • Installation works for underground building communications are ongoing.

Building 6

  • Monolithic frame of the building has risen by 2 floors – ongoing concrete work for vertical structures and elements of the 20th floor from 22 to 24.
  • Continued construction of external and internal walls at levels 14-15.
  • Works on the construction of underground parking under buildings 5-6 are ongoing.

Continuing construction of the monolithic frame of the educational center for children.

Continued works on the installation of internal courtyard engineering networks.

These updates reflect the active progress and commitment of City One Development to delivering high-quality residential and commercial spaces in the “Novopecherski Lipki” quarter.