The investment and development company, City One Development, continues to actively construct the premium-class residential complex, Novopecherski Lypky, despite all external circumstances.
Learn about the progress and noticeable changes in the new buildings of the 7th and 8th phases of the construction in our latest report:
Phase 7
Building #1
✅ Installation of aluminum window frames, glazing, and installation of window and door structures on the upper floors of the building is almost complete.
✅ We continue to insulate the building with non-combustible mineral wool.
✅ Finalizing the attachment of the protective geomembrane, installation of profiles, and arrangement of a ventilated facade with ceramic granite.
✅ Work on engineering networks for water supply and sewage, as well as low-current signaling and automation systems, is ongoing.
✅ We have completed the installation of the heat point for buildings 1 and 2.
✅ Work continues on the installation of architectural facade lighting.
Building #2
✅ Installing aluminum window glazing and window and door structures on the facade from the 14th to the 24th floors.
✅ Continuing work on insulating the building with non-combustible mineral wool, attaching protective geomembranes, and installing profiles for a suspended ventilated facade.
✅ Engineering work on water supply and drainage systems, low-voltage signaling and automation systems, supply and exhaust ventilation, and water supply pump systems is ongoing.
✅ Finishing work on the installation of the fire alarm system, as well as heating, sewage, and water supply systems in the underground parking between buildings 2 and 3.
✅ Completing brick wall laying, industrial floor construction, and installation of lights.
✅ Completed installation of paving stones on the ramps of the parking entrance group.
✅ Installing architectural facade lighting.
Building #3
✅ Completing installation of aluminum window glazing and window and door structures on the facade.
✅ Continuing insulation work with non-combustible mineral wool and attaching protective geomembranes.
✅ Installing profiles for a suspended ventilated facade.
✅ Installing engineering networks for water supply and drainage, low-voltage signaling and automation systems, supply and exhaust ventilation, and pump stations.
✅ Starting testing work on launching elevator equipment.
✅ Installing architectural facade lighting.
Building #4
✅ We are completing the installation of non-combustible mineral wool insulation on the walls, fixing the geomembrane, installing the ventilated facade and aluminum window frames, and glazing the window elements of the facade.
✅ We are equipping the engineering networks for water supply and drainage, low-current alarm and automation systems, and supply-exhaust ventilation.
✅ The installation of architectural facade lighting is ongoing.
Phase 8
Club-style building #9
✅ Decorative pergolas have been installed on the roof of the building.
✅ The laying of brick external and internal walls has been completed.
✅ The installation of ventilation systems, water supply and sewerage risers, fire protection systems, alarms, dispatching, and automation continues.
✅ The laying of internal walls in the underground parking is ongoing.
✅ The installation of elevator equipment is in progress.
Building #5
✅ The construction of the monolithic frame of the building has been completed, and the roofing works have been carried out.
✅ The laying of internal and external brick walls on the upper floors is in progress.
✅ The installation of ventilation systems, water supply and sewage risers, fire protection systems, alarm systems, dispatching and automation systems is ongoing.
Building #6
✅ The construction of the monolithic building is ongoing. The construction of the 7th floor has been completed, the slab between the 7th and 8th floors has been poured, and the reinforcement and concreting of the vertical structures of the 8th floor are in progress.
✅ The laying of external and internal walls from the 1st to the 5th floor is continuing.
✅ Works on the arrangement of the parking lot under building #6 are in progress.